MieresCAUDAL BASIN AREA
📍 Avenida del Camino nº 6 · Nuevo Santullano · 33600 Mieres
Strategic node: home to the Mieres 7750 router and the collection point for the Caudal, Aller and Nalón basins over direct fibre.
Towns served by this node
FigaredoRioturbioSanta Cruz de MieresTurónUjo
One of the contract's two new routers (PF-2) is installed here in Phase 1, interconnected with the Gijón PAO to share the load of the new OLTs.
OLT equipment in service
| OLT | Current equipment | Cards | GPON ports act./tot. | ONT |
|---|---|---|---|---|
| MIE/2A | Alcatel 7342 | 16 × GLT2A (2 ports) | 32 / 32 | 355 |
| MIE/2B | Alcatel 7342 | 16 × GLT2A y GLT2B (2 ports) | 32 / 32 | 344 |
| MIE/7A | Alcatel 7342 | 15 × GLT2A y GLT2B (2 ports) | 29 / 30 | 345 |
| MIE/7B | Alcatel 7342 | 7 × GLT2A y GLT2B (2 ports) | 14 / 14 | 87 |
| Node total | 1131 | |||
Week 27site survey & start
Week 35end of migration
9 weekstotal window
1131 ONTto migrate
Contract actions affecting this node
PF-1 · Replacement of its OLT with a dual GPON/XGS-PON unitPF-2 · Installation of a new router (Phase 1)PV-1 · New ONTs for users whose ONT lacks capacityPV-2 · New ONTs for users with incompatible ONTs