ColombresEASTERN AREA
📍 c/ Bajo Badalán s/n · 33590 Colombres (Ribadedeva)
Primary node with OLT, CATV, DC power and climate control.
Towns served by this node
Colombres
The last node of Phase 2: its migration closes out the network renewal in week 58.
OLT equipment in service
| OLT | Current equipment | Cards | GPON ports act./tot. | ONT |
|---|---|---|---|---|
| COL/1A | Ericsson BLM 1500 | 2 cards of 8 ports each | 5 / 16 | 74 |
Week 54site survey & start
Week 58end of migration
5 weekstotal window
74 ONTto migrate
Contract actions affecting this node
PF-1 · Replacement of its OLT with a dual GPON/XGS-PON unitPV-1 · New ONTs for users whose ONT lacks capacityPV-2 · New ONTs for users with incompatible ONTs
Rest of the pliego's plans